Construction
Facts & Figures June 2011
Total Reinforcement completed: 21,200.00 tons
Total Formwork completed: 44,360.00 sq.m
Total Hollow Core Slab completed: 29,120.00 sq.m
Total Pour Concrete completed: 92,410.00 cu.m
Total Manpower on Site: 3,370,150 hours
Number of injuries: 0
1 August 2011
Tower 1: Casting of L6 beam in progress.

Tower 2: Construction of L5-L6 Columns in progress.

Tower 3: Concrete placing booms installation in progress

Tower 4: Casting of P3 beams in progress

July 5 2011
Tower 1: Construction of Core wall L7-M7 and Columns at L5-L6 completed. Beams at L6 in progress.

Tower 2: HCS Topping at L5 completed, Core wall rebar works at L6-M6 and column rebar at L5-L6 in progress.

Tower 3: Rebar and casting for columns at L5-L6 and construction of core wall at M6-L7 in progress.

Tower 4: Casting of HCS topping P2, Core wall rebar work at L5-M5 and Column rebar work at P2-P3 are in progress.

19 June 2011
Tower 1 - Construction of beams and cast-in situ slab at M5 level in progress.

Tower 2 - HCS installation at L5 and Tie Beams Rebar work for L5 in progress.

Tower 3 - Rebar works for column at L5-L6 and core wall at M6-L7 in progress.

Tower 4 - Rebar work for P2 beams and rebar works for core wall at L5-5M and scaffolding works for columns at P2-P3 in progress.

5 June 2011
Tower 1: Construction of Columns for L5-L6 and rebar works for Corewall at L7-M7 in progress.

Tower 2: Rebar and casting of L5 beam in progress.

Tower 3: Rebar installation for Corewall at M6-L7 and construction of Columns for L5-L6 in progress

Tower 4: Rebar and casting of P1-P2 columns and rebarworks for corewall at L5-5M in progress.