Construction

Ground works have been completed, which included the excavation work for the four towers and the leveling of the site. Progress to date:

  • Piling Works for all four towers completed
  • Rafts for four towers completed in November 2009
    • Tower 1 Raft Pour – 27th August 2009
    • Tower 3 Raft Pour – 10th September 2009
    • Tower 2 Raft Pour – 1st October 2009
    • Tower 4 Raft Pour – 12th November 2009
  • Water proofing for rafts of all towers completed.
  • Construction of Corewall completed up to the following:
    • Tower 1: Podium Level L12
    • Tower 3: Podium Level M9
    • Tower 2: Podium Level M9
    • Tower 4: Podium Level L8
  • Construction of columns completed up to the following:
    • Tower 1: Level 9
    • Tower 3: Level 8
    • Tower 2: Level 7
    • Tower 4: Level 6
  • Installation of Hollow Core Slabs completed up to Level 9 for Tower 1, Level 7 in Tower 3, Level 6 in Tower 2 and Podium Level 5 in Tower 4.
  • Construction of beams completed up to the following:
    • Tower 1: Level 9
    • Tower 3: Level 8
    • Tower 2: Level 7
    • Tower 4: Level 5
  • Shoring and installation of panels around the site boundary 100% completed.
  • Tower cranes installed and operational at four towers.
  • External Hoist installed and operational for all towers.
  • Concrete Placing Boom installed and operational in all four towers.

1 June 2013

1 October 2012

14 May 2012

26 March 2012