Construction
Facts & Figures November 2011
Total Reinforcement completed: 23,055 tons
Total Formwork completed: 58,594 sq. m
Total Hollow Core Slab completed: 31,857 sq.m
Total Pour Concrete completed: 94,100 cu.m
Total Manpower on Site: 4,508190 hrs
Number of injuries: 0
Piles:
Total Concrete: 69,400 cu.m
Total Reinforcement: 17,25 0 tons
24 Jan 2012
Tower 1: Casting of Beam at L8 in progress.

Tower 2: Rebar work for columns at L6-L7 and core wall rebar work at L7-L8 in progress.

Tower 3: Casting of Toppings at L7 and rebar work of columns at L7-L8 in progress

Tower 4: Core wall rebar work at L6-L7 (2nd stage) in progress.

15 December 2011
Tower 2: Casting for beams at L6 in progress

Tower 4: Casting for internal slab at L5 in progress

Tower 1: Casting of Toppings & and construction of columns at L7-L8 in progress

Tower 3: Construction of columns L6-L7 in progress.

30 November 2011
Tower 1: Casting of Toppings & Laying HCS L7 and construction of columns at L7-L8 in progress.

Tower 2: Casting of core wall at M6-L7 completed and fixing rebar for beams at L6 in progress.

Tower 3: Core wall rebar L7-L8 and scaffolding for columns at L6-L7.

Tower 4: Rebar and casting for HCS toppings at L5 in progress.

15 November 2011
Tower 1: Beam L7 Rebar work, Laying HCS L7 and construction of columns at L7-L8 in progress.

Tower 2: Core wall rebar work at M6-L7 in progress and fixing placing boom.

Tower 3: Preparation work for core wall rebar installation at L7-L8.

Tower 4: Rebar work for HCS toppings at L5 in progress.